Project State and Percent Complete Changes Inconsistently Based on the Deletion Order of Project Tasks With Different StatesIssue Project state and Percent Complete changes inconsistently based on the deletion order of project tasks with different states.Steps to reproduce : 1.Create 3 projects (PRJ_A, PRJ_B, PRJ_C), and then create 3 project tasks (PRJTASK_01, PRJTASK_02, PRJTASK_03) under each project. 2.Update the states of the project tasks as shown below. (PRJTASK_01) : Pending(PRJTASK_02) : WIP(PRJTASK_03) : Closed Complete==>PRJ_A (State : WIP, Percent complete : 33.33%)- PRJTASK_01 (Pending) - PRJTASK_02 (WIP) - PRJTASK_03 (Closed Complete) PRJ_B (State : WIP, Percent complete : 33.33%)- PRJTASK_01 (Pending) - PRJTASK_02 (WIP) - PRJTASK_03 (Closed Complete) PRJ_C (State : WIP, Percent complete : 33.33%)- PRJTASK_01 (Pending) - PRJTASK_02 (WIP) - PRJTASK_03 (Closed Complete) 3.Delete 2 tasks from each project and leave one remaining task as shown below. (PRJ_A) : Delete PRJTASK_02 and PRJTASK_03 => Remain PRJTASK_01 (Pending)(PRJ_B) : Delete PRJTASK_01 and PRJTASK_03 => Remain PRJTASK_02 (WIP)(PRJ_C) : Delete PRJTASK_01 and PRJTASK_02 => Remain PRJTASK_03 (Closed Complete)==>PRJ_A (State : Pending, Percent complete : 0%)- PRJTASK_01 (Pending) PRJ_B (State : WIP, Percent complete : 0%)- PRJTASK_02 (WIP) PRJ_C (State : Closed Complete, Percent complete : 100%)- PRJTASK_03 (Closed Complete) 4.Delete the remaining project task. (PRJ_A) : Delete PRJTASK_01 (Pending)(PRJ_B) : Delete PRJTASK_02 (WIP)(PRJ_C) : Delete PRJTASK_03 (Closed Complete)==>PRJ_A (State : Pending, Percent complete : 0%)PRJ_B (State : WIP, Percent complete : 0%)PRJ_C (State : Closed Complete, Percent complete : 0%) All three projects end up with no remaining project tasks; however, each project retains a different state (Pending, WIP, or Closed Complete).Especially PRJ_C, the state is Closed Complete, but Percent complete is 0%, this is a mismatch. Release All Resolution The issue is due to PRB2080201 and is fixed in Canada.