Project Tasks are not displayed in the Planning ConsoleIssue Not all project tasks for a particular project are visible on the Project Console.CauseThe Planning Console is very 'finicky' about what sub-projects and project tasks are displayed. If there is an issue with the project (as discovered by Project Diagnostics), the affected project tasks will not be displayed. In this case, there were invalid relationships.ResolutionRun Project Diagnostics on the project, then click into the failure, click on the link to open the affected records, and delete the dependency record(s).Then use the Recalculate Project option in Project Diagnostics to recalculate the project.