All Risk response tasks are not moving to Work in progress state but the last Update task is moving to Work in progress.Issue Risk Management application to continuously monitor to identify high-impact risks, improve your risk-based decision-making, and reduce reaction time effectively.The issue is all risk response tasks are not moving to Work in progress state but the last update is moving to Work in progress. Steps to reproduce:1. Open the risk which is in a Review state.2. Now click on the respond ui action which changes the risk to New.3. But only the recent task is moved to Work in progress.CauseThis is the expected behavior, as per the OOB code configuration. The Respond UI Action calls a Script Include which changes the main risk record to Work in progress and the last updated task to Work in progress.