Unable to update the "Planned effort" Field from the New Project WorkspaceDescriptionUnable to update the "Planned effort" Field from the New Project Workspace since it clears out shortly after setting the value.Steps to Reproduce Go to "pm_project_task.LIST"Set your View to "Project Workspace"Personalize the list to include "Planned effort"Open any Project and go to the New Project Workspace Planning ConsoleAdd any value to the "Planned effort" Field and see it does not updateYou can also try adding two Project Tasks, one Parent, one Child.Give the child some Planned Effort on the Form ViewOpen the New Project Workspace and set the Parent Planned Effort and see it gets cleared when it should not beWorkaroundThis problem is currently under review. You can contact ServiceNow Technical Support or subscribe to this Known Error article by selecting Subscribe in the options at the top of this article to be notified when more information becomes available.Related Problem: PRB1581861