The "Planned end date" on Release Records is not being set to the Selected ValuesIssue You are finding that the "Planned end date" Field on your Release Form is not being set to the Selected Value. Instead it is updating to be 1 day ahead of the "Planned start date" Field and this happens even when you are specifically setting it to another date.CauseMost likely this is happening because the Duration "duration" Field is missing from your Form Layout on the Release Records. Since the "Planned end date" Field is being calculated from the Duration "duration" Field then it is required for this Field to be displayed on the Form Layout. Otherwise the Duration "duration" will be set as 1 day (the Default Value) and the Release "Planned end date" will be recalculated as Planned start date + 1 day.ResolutionPlease ensure the Out Of Box Duration (duration) Field is displayed on your Release Record Form Layout.