Requested Allocations are not being created for Resource PlansIssue When creating a Resource Plan you are seeing that the Requested Allocations have not been created. Additionally you are seeing the following Error: Cannot create Requested Allocations as there are no working days in the schedule for the plan date rangeCauseThis is happening because the Project that is linked to the Resource Plan does not have a Valid Schedule associated to it.ResolutionPlease check the "Schedule" Field of the associated Project RecordEnsure there are Working Days in the ScheduleIf needed you will need to Create a Schedule for thisYou can then set the Default Project Schedule by setting the "com.snc.project.default_schedule" System PropertyFor reference on the above please see the "Setting a new default Project Schedule" Article Here