State update of project is not reflecting on project taskIssue Project is to create and manage small projects with a few tasks to large portfolios that contain complex tasks with various relationships and dependencies. State of the project task is not changing as per the update on the project. Steps to reproduce: Open the projectsChange the state to Onhold in project task which would change the state and projectNow change the state to work in progress on project which should change the state of project task as wellCauseIt is an expected behavior wherein if any of the project start date is after the Project constraint date then those tasks state will not be changed by this action. Below message would be shown in the popup. "All project tasks with same start date as the project constraint date or before will be set to Work In Progress. Are you sure you want to continue?"ResolutionVerify the start date scheduled and the constraint date. If it is not unique to that day, try to verify and adjust the intended start date.