When Project is imported from MS Project, project and project tasks display an incorrect order on the Planning Console DescriptionWhen user tries to import a MS Project file into the project planning console, sub projects tasks show up under the correct project tasks but the order of both the main tasks and subtasks do not match the order from the .mpp file Steps to reproduce:1. Navigate to: Project > Projects > Import Project2. Select mpp file3. Create New Project with "Calculation Type: Automatic"4. Import5. Open newly imported project in the Planning ConsoleRelease or EnvironmentRomeCauseIssue is due to the usage of an outdated Processor "OldMSProjectImportProcessor". Resolution To resolve the issue: 1. Go to System Definition > Processors 2. Search for "OldMSProjectImportProcessor" and go to the record *Link: /nav_to.do?uri=sys_processor.do?sys_id=ea54521137101000bff8e0f617733428 3. Uncheck the Active checkbox 4. Save