Planned Dates in Release Phase and Release Task are autopopulated with the Release Planned DatesIssue Planned start dates for Release Management process are being set based on the value of the parent and not updated based on the value of the child tasksCauseThis is happening because by default Time Constraint field for the release child records is set to ASAP( As soon as possible) for new record, which means release tasks date needs to be the same as the Release date. Out of the box we have not added time constraint field in the Release Task or Phase forms, so the system takes the default value (ASAP). ResolutionThe field Time Constraint can be added to both the Release Task and the Release Phase records so it can be set to the option that would best suit the process.Alternatively, a before BR can be created to automatically set the value of the field.You can find more information regarding the Time constraint options here