Status getting updated twice on the RITMDescriptionClosed Complete status getting updated twice on the audit of the RITM.CauseFor the affected flow, on action 3, the Stage is getting updated as "Completed" and the State is getting completed as "Closed Complete". As per the OOTB functionality, if the Stage of the RITM is updated as Completed, the State of the RITM gets automatically updated as "Closed Complete". This is an expected OOTB behavior. Here, as you are updating both stage and state through the flow action, hence two updates of the state field are shown. On the affected flow, on removing the State getting updated and I can see that now only one update is shown on the RITM.ResolutionYou can update the Stage as Completed which will anyways update the State of the RITM as Closed Complete.