Utilization in Resource Workbench and Scenario Planning does not MatchIssue There is a discrepancy on the resource utlization seen on Capacity Workbench and the utlization seen on Portfolio Planning Worbench -> Resource For example: Create a Test Resource Group with user Dummy Resource.User schedule is 4h a day. Assign a Resource Plan to the user with 176 planned hours Navigate to Capacity workbench and open the project/demand for that resource planThe Utilization is 200% Open the same on Portfolio Planning Workbench Utilization is 100% Now, change the schedule to 8h and repeat the operation, both workbench will show 100% utilization.ResolutionWhenever we change a schedule hours of the user, then it is recommended to update the capacity of the user from the form. [UI Action for updating capacity is available in the form] So, that it updates the capacity in aggregate tables. Resource Management [Capacity Workbench] tries to calculate the utilization on the fly using users schedules instead of depending upon the aggregate monthly tables. Where as, Scenario Planning [Portfolio planning workbench] tries to calculate the utilization using user capacity in resource_aggregate_monthly table. Hence, It is required and recommended to update the users capacity after we change the schedule of the user.