Planned end date on program record is not rolling up properly from program tasksIssue Program planned end date is not synched with program task planned end date in Project Portfolio Management (PPM) module.CauseThe above-mentioned functionality is expected behavior on out-of-box (OOB) where we do not roll up/sync the planned end dates if they are earlier dates than initially provided. We are only rolling up the planned end dates on the program from program tasks that are extending (meaning if we change the program task planned end date to future date to earlier provided dates then they will roll up to program planned end date). Example: current program task planned end date is set to Dec 31, 2021 and if we change it to Jan 31, 2022 or any other future date to earlier provided date then they will roll up to program planned end date.ResolutionWorking as designed