MS Project Export - Schedules and File ExtensionsIssue MS (Microsoft) Project Export within ServiceNow assumes a 8:00 AM - 5:00 PM Schedule is used. Whenever the file is exported, you will only get .XML files, not .MPPResolutionFrom the ITBM Product team:It is expected that the exported extension is .xml rather than .mpp. We export it as Microsoft Project XML file format which is the supported format for importing XML files. Additionally, the export expecting a schedule of 8:00 - 5:00 is also expected behavior currently. We only support the 8:00 - 5:00 schedule for import which is why we only allow "Project Management Schedule" or the "Default MS Project" Schedules, which are 8:00 - 5:00 unless customized, which would not be supported.