Currency Conversion Issue on Cost PlansIssue When the user tries to create the cost plan with entered currency as different to functional currency/project currency then the conversion is happening with 1:1 ratio instead of the defined budget reference rates.CauseThe budget reference rates were defined from GBP to AED and AED to GBP currencies starting (Start Date) 01/07/2021The fiscal year is set to start from April and the customer created a cost plan with start fiscal period FY21:M06 which does not fall under the start date of budget reference rates So for the selected fiscal period ( FY21:M06), the start date is 01/10/2020 but the reference rate start date is mentioned as 01/07/2021 hence the conversion did not happen as definedResolutionCreating a cost plan with a fiscal period start date as 01/07/2021 or a later date will convert the entered currency into functional currency with a defined reference rate from the budget reference rate records