Exporting a project with subprojects to MS project fails to export restraint dates correcty causing wrong import in MS project


Description

When exporting a project to Microsoft Project restraint dates are not exported correctly. This causes the project to have incorrect dates when imported into Microsoft Project.

Steps to Reproduce

1. Have a project with subprojects
2. Export the project from ServiceNow to Microsoft project
Before attempting to use the file for import, observe dates on the imported subprojects are wrong.

Workaround

This problem has been fixed. There is no workaround available. If you are able to upgrade, review the Fixed In section to determine the latest version with a permanent fix your instance can be upgraded to.


Related Problem: PRB1497156