Total Planned Cost is not getting updated in Demand when Cost Plans are inserted or updated. Task Type Breakdown is not generated either.Issue Total Planned Cost is not getting updated in Demand when Cost Plans are inserted or updated. Task Type Breakdown is not generated either.ResolutionThis was happening due to the customization of the "Restrict Duplicate Breakdown of Type Req" Business Rule on Cost Plan Breakdown. Once reverted, the Planned Cost will roll up to the Demand and the Task Type Breakdown is generated. To do so, follow the steps below. NEXT STEPS: 1. Navigate to System Definition > Business Rules 2. In the "Name" column search for "Restrict Duplicate Breakdown of Type Req" and go to the record 3. In the Versions related list, Right-Click the record with the Source of "System Upgrades: VersionName..." 4. Select "Revert to this version" 5. Select OK when prompted