Dependency field on projects is empty and cannot be exportedSummary The Dependency field on a project record is empty by design. It is a decoration-type field that is calculated and populated only at runtime, then cleared. Because it holds no persistent value, it cannot be exported. All dependency information is stored in the Planned Task Relationship [planned_task_rel_planned_task] table. The Dependency field defines a logical relationship between two tasks based on Predecessor and Successor values. It controls scheduling order but does not persist a value after runtime calculation. To verify this, open a project record and append .do?XML to the record URL — the Dependency field will appear empty in the XML output. Added context from ServiceNow docs: The Dependency field supports relationship types such as Finish-to-Start (FS), Start-to-Start (SS), and Finish-to-Finish (FF) between tasks. A Finish-to-Start dependency means a successor task cannot start until its predecessor finishes. For task dates to shift automatically based on dependencies, the Time Constraint field on the task must be set to Start ASAP, which is the default setting. Dependencies can be created through the Planning Console, Project Workspace timeline, or the task record's Dependencies related list. Because the Dependency field has no persistent value, it cannot be exported. All dependency data is stored in the Planned Task Relationship [planned_task_rel_planned_task] table. Related Links Project Task Dependencies Not Exported Project task relationships and dependencies