Project Task Dependencies Not Exported


Description

The XML import for projects/project tasks has been done, but the project task dependency is not populated.

Cause

The dependency field is not populated directly on the planned task record, the field type is 'decoration'. Development has indicated that this column does not have a value and is calculated and filled in at runtime and is based on the "Planned Task Relationships (planned_task_rel_planned_task)" table. This is why the value cannot be exported or reported on from planned task since there really is no value in this field. 

Resolution

If you are importing all project task records, the records from planned_task_rel_planned_task can be exported with the list view as well. If you are just working with a particular project, use the 'Export
to xml' UI action from the form context menu of the top project.