Resource Plans on Project Tasks do not move dates as expected with the Project TaskDescriptionWhen the "com.snc.project.date_change_cascade" System Property is set to TrueChanging the 'Planned start date' from a Project Task Form is not updating the Resource Plan Dates for that Project Task.Steps to Reproduce 1. Ensure that "com.snc.project.date_change_cascade" System Property is set to True2. Create a Project3. Create a Project Task on the Project4. Create a Resource Plan on the Project Task level5. Go to the Project Task Form View6. Set the Planned start date to next month7. Save the record8. See that the Resource Plan Dates do not changeWorkaroundThis is expected behavior and by design in all currently supported releases.Related Problem: PRB1498366