Actual Hours are not being calculated against a project resource plan.


Description

Actual hours are not being calculated after assigning and approving a time card against a resource plan.

Release or Environment

Quebec

Cause

Date for time card not adding in alignment with resource plan date range.

Resolution

Please ensure the following when submitting a timecard against a resource plan:
1. The dates selected are within the date range for the resource plan*
2. The project/task is selected
3. The user is selected
4. The resource is selected
5. The time card is processed.

*For time card - if the week starts on selected is 5/9 but the resource plan date starts on 5/12 any hours added on days before 5/12 won't be included on the actual hours for the resource plan.