Actual Hours are not being calculated against a project resource plan.Issue Actual hours are not being calculated after assigning and approving a time card against a resource plan.ReleaseQuebecCauseDate for time card not adding in alignment with resource plan date range.ResolutionPlease ensure the following when submitting a timecard against a resource plan: 1. The dates selected are within the date range for the resource plan*2. The project/task is selected 3. The user is selected 4. The resource is selected 5. The time card is processed. *For time card - if the week starts on selected is 5/9 but the resource plan date starts on 5/12 any hours added on days before 5/12 won't be included on the actual hours for the resource plan.