Cost in Project / Demand Currency is using the wrong Exchange Rate / Showing the Incorrect ValueIssue When creating a Resource Plan / Cost Plan on a Project / Demand you are seeing that the Total planned cost / Actual cost in Project/Demand Currency is showing an unexpected or incorrect value.CauseThis is most likely happening because the Budget Reference Rates have not been set properly for this Exchange Rate. Therefore the Resource Plan / Cost Plan is using the wrong Rate to calculate the Exchange. Please also ensure that the "com.snc.resource_management.use_budget_reference_rates" System Property is configured in the instance and set to the value = true.ResolutionPlease navigate to the 'Budget Reference Rates' Module and ensure that you have updated the Budget Reference Rates to contain the latest rates which you are wanting to use in your instance. Please see our 'Currencies and budget reference rates' Documentation for any assistance with this.