Unrealistic Time Elapsed value is displayed in Project Workspace - Analytics tabDescriptionUnrealistic Time Elapsed value is displayed in Project Workspace - Analytics tab ResolutionThis is happening because the Project is in the Work in Progress state but there is no Actual Start Date for the Project. Once this is fixed, the Time Elapsed should render a more realistic value. This can be fixed by Recalculating the Project. To do so, follow the steps below. Next Steps:1. Navigate to the Project 2. Click the "Project Diagnostics" Related Link 3. Run the "Recalculate" Diagnostic