How does the Scenario Planning Workbench pull in Percent (%) Utilization?Issue How does the Scenario Planning Workbench pull in Percent (%) Utilization?ResolutionWe do not factor in Operational Work to the Percent Utilization on the Scenario Planning Workbench. We look at the "resource_aggregate_daily" table and gather the "Project Confirmed", "Project Allocated", and "Capacity" categories for each user in the given Group. "Non-project Time" is excluded.After we gather all of the Capacity and Project related Aggregates, we perform the following calculation: (Project Confirmed + Project Allocated) / Capacity The majority of this behavior resides in the "ScenarioRMService" Script Include.