<h2>Not all relevant financials in Project Financials are shown as Capex</h2><br/><div style="overflow-x:auto"><article><div ><h3 >Issue </h3><section><ul><li>In the Expense lines, all are marked as Capex, but in the Financials overview, only a partial amount(EG: 623.73K out of 725.95K) shows up as Capex.</li><li>The rest of the amount doesn't show up at all.</li></ul></section></div><div ><h3 >Release</h3><section><ul><li>Paris</li></ul></section></div><div ><h3 >Cause</h3><section><ul><li>This is the expected behavior.</li><li>The OPEX and CAPEX below the Actual cost on the Financial Tab come from the Cost Plan Break downs Table.</li></ul></section></div><div ><h3 >Resolution</h3><section><ul><li>Go to the cost plan breakdown Table of the project</li><li>Now show matching for Capex > Take out Sum</li><li>The sum of the actuals shown in the Expese Type: CAPEX will be similar to the Financials Tab amount.<br /></li></ul></section></div></article></div>