Resource Report with Epic


Description

Resource Management Application's Resource Report doesn't work with SAFe entities. If you select the "Portfolio" level and selected the wanted portfolio to the resource report and ran the report, it doesn't show anything.

 

Steps to Reproduce:

Release or Environment

Paris

Cause

Resource Reports are not integrated with Epics.

Only Projects and Demands are integrated with Portfolio

Resolution

 In order to look for the Resource Plan associated with the Epic, please select the Entity Type as 'Other Task' > Enter the Short Desc of the Epic > You will see the Resource Plans associated with the Epic