Project Approved Start/End Date field values do not match Planned Start/End Date values when creating Project from DemandIssue Project Approved Start/End Date field values do not match Planned Start/End Date values when creating Project from Demand. When creating a Project from a Demand using the 'Create Project' related link, the Approved Start Date and Approved End Date values do not match Planned dates exactly.CauseThis behavior is by design.ResolutionThis behavior is by design. Demand start/end dates pulled into Project during DemandToProject creation do not consider the Project's internal schedule when setting values for Approved Start/End Date. While they do match the Demand's Start/End date, the time values used will be the start/end of the respective calendar days. Time will be set to a default value (first of the day or last of the day): 00:00:00 -> 23:59:59 OR 12:00:00 AM -> 11:59:59 PM