Closing a Project resets all Project Task's Percent Complete to 0Issue When closing a Project, the Percent Complete values of all children Project Tasks sets to 0.CauseBusiness Rule: Task Active State Management comes OOB with an Order of 50. If this order is updated, it may cause the Business Rule to run and override state (which updates percent complete) at incorrect times during the update transaction.ResolutionEnsure that the Task Active State Management Business Rule is set to it's OOB Order of 50.