Closing a project resets percent complete to 0 for all project tasksIssue When a project is closed, the percent complete value of all child project tasks resets to 0. The Task Active State Management business rule has a default order of 50. If the order is changed, the business rule can run at the wrong time during the update transaction. The business rule then overrides the state, which updates percent complete. Release All Cause The Task Active State Management business rule has a base system order of 50. If this order is updated, the business rule may run and override state (which updates percent complete) at incorrect times during the update transaction. Resolution Set the order of the Task Active State Management business rule to the default value of 50. Open the Task Active State Management business rule record. Check the value in the order field. If the order is not 50, change it to 50. Save the record.