Copy Project UI action is not copying project tasksIssue Creating the Project using the "Copy Project' UI Action is not creating the project tasks under the newly created Project. Steps to Reproduce: Navigate to the project list.Check for the project which contains sub-project and that sub-project also contains project tasks.Open sub-project and check for the project tasks which it contains.Right-click on sub-project header, and click on ‘copy project’ UI Action.Fill the details asked for and click on OK to create the project.Check the newly created project you can find project tasks not created/copied.Open the sub-project which has been copied, project tasks created on this project, not on the newly created project.CauseUnder Project Properties Under List of Additional Attributes> You might have added Parent fieldResolutionIf you remove the Parent field from the List of Additional Attributes Section, the Project tasks will get created as expected.