Financials Summary - Budget Cost different from Opex and Capex sum. project_funding records different from ProjectIssue Financials Summary - Budget Cost different from Opex and Capex sum. project_funding records different from ProjectResolutionThis was happening because of a Cost Plan Breakdown with a Budget Cost populated in a Fiscal Period the Project was not in based on the Planned Start and End Dates.To fix this we can clear out the Budget value for the related Cost Plan Breakdown record. To do so, follow the steps below.[code]Next Steps:[/code]1. Navigate to "cost_plan_breakdown.LIST"2. Filter by the Task of the project number and where Budget is greater than 0 and go to the record(s)3. Right-click the form header and select Configure > Form Layout4. Add the Budget field to the form and save5. Set the Budget to 06. Save the form. Now the Budget Cost will be correct the next time you update it.