Planning console Infinite LoadingIssue One project in the planning console, when adding tasks or clicking on unindent option is going to e have an infinite loop CauseCould be caused for the following issues with project: All tasks in Pending/Open state that have an actual start date need to be set to "Work In Progress" or There are invalid tasks (Project tasks are in WorkInProgress state but Actual Date is not populated) in this project which is causing this issue or All tasks that were at 100%, having actual start and end date need to be closedResolution- All tasks that were at 100%, having actual start and end date need to be closed - set them to close complete; - All tasks in Pending/Open state that have an actual start date need to be set to "Work In Progress";- There are invalid tasks (Project tasks are in Work In Progress state but Actual Date is not populated) set Actual Date;