Roll up of resourcing from Child to ProjectIssue Why the resource plans are moving from child project to Parent? The resource plans are on the Child Project and they should not be rolled up to the parent When we open the parent project, and scroll down to the resource plan tab, we can see resource plan showing here as well.CauseThe above is working as expected and as per design. The resource plans are just showing up on the parent since the top task for the child project is mapped as a parent. No new resource plans are getting created for parent project, it is just that the child-parent resource plans are shown under parent as well. This happens via the defined relationship. Please see below link: https://<instance-name>.service-now.com/nav_to.do?uri=%2Fsys_relationship_list.do%3Fsysparm_query%3DnameSTARTSWITHresource%26sysparm_first_row%3D1%26sysparm_view%3D%26sysparm_choice_query_raw%3D%26sysparm_list_header_search%3Dtrue