Planning console date values change erratically


Description

When indenting sub-tasks in client side planning console new parent (contains dependencies) of existed child tasks, dates are jumping.

Steps to Reproduce

  1. Create Project and tasks t1, t2 and t3.
  2. Create sub tasks t2.1, t2.2 to t2.
  3. Create 1fs+0 dependency from t1 to t2.
  4. In client side planning console, indent task t3 to t2 then we can see t2.1, t2.2 and t2 task dates will change incorrectly.

Workaround

This problem has been fixed. If you are able to upgrade, review the Fixed In section to determine the latest version with a permanent fix your instance can be upgraded to.

When clicking the save button, dates are reset to what they should be, so to not see this issue in client side planning console.


Related Problem: PRB1371194