Resource Plan's Start Date is getting moved when the Project's Start Date is changed. This causes the Resource Plan to move back into a Requested state when previously Confirmed.DescriptionResource Plan's Start Date is getting moved when the Project's Start Date is changed. This causes the Resource Plan to move back into a Requested state when previously Confirmed.CauseUpon investigation, it was found that this is indeed the expected behavior if you have the "com.snc.project.date_change_cascade" System Property enabled.If you disable this System Property, the Resource Plan Start Date will remain and the State of the Resource Plan will not change.ResolutionTo disable the System Property, follow the steps below.NEXT STEPS:1. Navigate to System Properties > All Properties2. In the "Name" column search for "com.snc.project.date_change_cascade" and go to the record3. Change the text in the Value field to "false"4. Save the record