Not able to Recreate Cost Plan Breakdowns for Cost PlanIssue Not able to Recreate Cost Plan Breakdowns for Cost Plan.CauseThis was happening due to improper Fiscal Period records.ResolutionNEXT STEPS:1. Navigate to Fiscal Calendar > Fiscal Periods2. Make sure the Dates are proper and if not fix them3. Go to the related Resource Plan record4. Change the Planned End Date to be in a different month5. Change the Planned End Date back to what it should be. This will allow the necessary scripts to regenerate the Cost Plan Breakdowns for the Cost Plan.