Move Project UI Action not working for a specific Project record.


Description

Move Project UI Action not working for a specific Project record.

Cause

Upon investigation, I found that this was not working due to a customized Business Rule called "Recalculate" on the planned_task table.
After reverting this to the latest OOB version, everything should work as expected.

Resolution

  1. Navigate to System Definition > Business Rules
  2. In the Name column, search for "Recalculate" and go to the Active record
  3. In the Versions related list, Right-Click the latest record with the Source of "System Upgrades: glide-VERSION-NAME..."
  4. Select "Revert to this version"
  5. Click "OK" when prompted