Planned End Date is incorrect on the project tasks and it's not calculated properly based on the planned durationDescriptionThere are multiple Project Tasks where the Planned End date got updated and it's matching up with the planned duration.CausePlanned Start Date, Planned End Date and Planned Duration fields are configured in two places. On the top of all the sectionsUnder the Dates sectionResolutionIf below fields are configured are in 2 places on the same form, Remove it from one either from the section or at the top of the form by navigating to Configure->Form Layout.