When accessing the Allocation Workbench , there is no data in the workbench


Description

Allocation Workbench for some of the Demands is not getting generated even the Demand has a resource assigned.

Release or Environment

Madrid Patch 7

Cause

Resource plans were created for Demands. For demands start and end date(due date) are not mandatory but these values are missing on the form.

Resolution

To show a demand on allocation workbench these dates should be populated. When entered start date and due date for one demand and data showing in workbench.