The Requested Item is marked to close complete from the flow designerIssue The Requested Item (RITM) is set to "close complete" without any value being set in the flow designer. Although there are multiple actions available, none of them sets the Requested Item (RITM) to "close complete." However, when the flow is completed, the Requested Item (RITM) is updated to "closed complete."CauseThe problem is caused by setting the stage value to "complete" just before the sub-flow action sets the Requested Item (RITM) state to "closed complete." Conducting a test in the out-of-the-box (OOB) environment and found that the behavior is the same: when the stage value is set to "complete," the RITM state is also set to "closed complete." However, in the other flow designer, noticed that the stage value is set to "complete" after the sub-flow action.ResolutionRemove the stage set to complete in the flow designer.