'Move Project' UI Action in Project is not workingIssue Steps to Reproduce: Create a project with a Planned start and end dateCreate a child taskNow "Move Project" UI action will be visibleNow click on "Move Project" UI action and select a new planned start date and click ok Actual: The planned start date is not updated Expected: The planned start date is updatedCauseBusiness rule "Recalculate" has been customized /nav_to.do?uri=sys_script.do?sys_id=3a3412b09f230200598a5bb0657fcf69 Resolution Restore the Business rule "Recalculate" to OOB state, it will work as expected.