Discrepancy between the "Planned Start Date" on demand and project formsIssue Discrepancy between the "Planned Start Date" on demand and project formsReleaseALLCauseDefault project schedule only runs Monday - Fridays. ResolutionThe behavior seen is due to the out of box default project management schedule seen here: <instance name>.service-now.com/nav_to.do?uri=cmn_schedule.do?sys_id=7aa3e10c8f70010040f82ab2f0f9234d The schedule is not running on the weekends, only weekdays. Since the project schedule does not run on Saturdays, it will start on the next available business day. If you are expecting Projects to start/end on weekends, the out of box project management schedule will need to be updated accordingly.