Planning Console is not showing any Project TasksDescriptionPlanning console is not getting loaded with any of the Project Tasks.CauseThe issue is due to corrupt data in dates of Project/Project Task. Check If, the Planned End date for project task's is earlier to the planned start date of the project, which is wrong.Check If, the Planned Start date for project task's is after the Planned End date for project task's, which is wrong. Check If, the Planned End date for project task's is earlier to the Planned Start date of the sub tasks which is wrong. Check If, Project tasks is in Work in Progress and don't have corresponding Actual Start Date.ResolutionFollow below steps to fix the dates in Project tasks: Export the project(Export to XML Context Menu), and import it in any out of the box /DEV instance.Fix the dates for these project tasks.Update the records and check if they show up in planning console.