Planned end date gets recalculated improperly when 'Start Project' button pressedIssue The planned end date gets recalculated improperly when the 'Start Project' button pressed. Steps to reproduce: 1. Enter a new project 2. Set Planned Start Date as of 10/12/2019 and Planned End Date as of 10/31/2019. 3. Press 'Start Project' Button 4. View Planned End DateReleaseAnyCauseCustomization on BR (business rule) : Recalculate (Called every time an Update happens on Certain Date Fields) or Client Script: Calculate End Date From Duration (Called when Planned Duration Changes)ResolutionIf any of these Planned Task Field Changes, these below 2 either/OR are called Planned Start DatePlanned End DatePlanned DurationActual Start DateActual End DateActual Duration BR: Recalculate (Called every time an Update happens on Certain Date Fields) /nav_to.do?uri=sys_script.do?sys_id=3a3412b09f230200598a5bb0657fcf69 Client Script: Calculate End Date From Duration (Called when Planned Duration Changes) /nav_to.do?uri=sys_script_client.do?sys_id=cef73b318f11010040f82ab2f0f9237a