Project Calculation type is changing to Manual after schedule uploadIssue Symptoms Project Calculation type will change after importing an MPP file ReleaseKingston Patch 4CauseThis is expected behavior ResolutionIn Kingston, Dates in the ServiceNow project remain the same as the dates in the Microsoft Project file - So to retain the dates same as the MPP file, we create all tasks as start on, and the project is made manual so that dependencies are not affected by the dates upon import. Related LinksImportMicrosoftProjectFiles