In Project Management, when importing a project created in v2 into v3 there is an issue with displaying the gantt chartDescription In Project Management, if you import a project created in v2 into v3 and try to view the gantt chart it does not display properly. The following message appears in the system log:ProjectGanttSchedulePage::_returnItemsFromptm null projectTasksAlso, the project tasks with sub-tasks may not roll up correctly. Steps to Reproduce Open Project Management.Import a project plan from v2 into v3.Click on the Gantt Chart UI action. Workaround The attached script file named update_migrate_projects.js can be used to migrate the v2 projects to v3 individually. The sys_id needs to be replaced with the desired project sys_id at line 7: roots.addQuery("sys_id", "SYS_ID"); In case the source [pm_project] table contains only projects to be migrated, the sys_id condition can be removed completely. Related Problem: PRB595181